Maintaining and improving water and sewer infrastructure is crucial for enhancing the quality of life in communities. These systems play a fundamental role in providing essential services that directly impact public health, environmental sustainability, and overall well-being.
Project at a Glance
The following areas are part of the PVC water main replacement in the water system in 2025
Creekview/Crosscreek Trail
- Budget - $2.4 million
- Construction is underway and is expected to be completed in November/December 2025.
Chandalar Lane
- Budget - $450,000
- Design complete
- Construction is expected to begin in January 2026. This is an eight-month project.
Hamilton Road
- $560,000
- Design complete
- Construction is expected to begin in January 2026. This is an eight-month project.